Project Data Sheet

Project Data Sheets (PDS) contain summary information on the project or program: Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

PDS Creation Date 05 Dec 2006
PDS Updated as of 14 Jul 2015

Project Name Power Rehabilitation Project
Country Tajikistan
Project/Program Number 32513-013
Status Closed
Geographical Location Tajikistan
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Sector Not yet classified
Subsector For Classification
Strategic Agendas
Drivers of Change
Gender Equity and Mainstreaming Categories

Financing

Type/Modality of Assistance Approval Number Source of Funding Approved Amount (thousand)
Technical Assistance3600Japan Special Fund500
Loan1817Asian Development Fund34,000
Loan-Islamic Development Bank9,300
Loan-Swiss Development Corporation6,000
Counterpart 13,588
TOTAL US$ 63,388

Safeguard Categories

For more information about the safeguard categories, please see http://www.adb.org/site/safeguards/safeguard-categories

Environment B

Summary of Environmental and Social Aspects

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples

Stakeholder Communication, Participation and Consultation

During Project Design
During Project Implementation

Description

Project Rationale and Linkage to Country/Regional Strategy

Development Impact

Project Outcome

Description of Outcome
Progress Towards Outcome

Outputs and Implementation Progress

Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Status of Development Objectives
Status of Operation / Construction
Material Changes

Business Opportunities

Date of First Listing 2006 Dec 05
Consulting Services
Procurement
Procurement and Consulting Notices
http://www.adb.org/projects/32513-013/business-opportunities

Timetable

Concept Clearance
Fact-finding 10 Apr 2000 to 25 Apr 2000
Management Review Meeting 19 Jul 2000
Approval 20 Dec 2000

Milestones

Approval No. Approval Signing Effectivity Closing
Original Revised Actual
Loan 1817 20 Dec 2000 26 Feb 2001 24 Aug 2001 30 Jun 2006 31 Dec 2008 23 Apr 2009

Utilization

Date Approval Number ADB (US$ thousand) Others (US$ thousand) Net Percentage
Cumulative Contract Awards
03 Sep 2015 Loan 1817 39,105 0 98.00%
Cumulative Disbursements
03 Sep 2015 Loan 1817 39,947 0 100.00%

TA Amount (US$ thousand)

Approval Number Approved Amount Revised Amount Total Commitment Uncommitted Balance Total Disbursement Undisbursed Balance

Status of Covenants

Covenants are categorized under the following categories—audited accounts, safeguards, social, sector, financial, economic, and others. Covenant compliance is rated by category by applying the following criteria: (i) Satisfactory—all covenants in the category are being complied with, with a maximum of one exception allowed, (ii) Partly Satisfactory—a maximum of two covenants in the category are not being complied with, (iii) Unsatisfactory—three or more covenants in the category are not being complied with. As per the 2011 Public Communications Policy, covenant compliance ratings for Project Financial Statements apply only to projects whose invitation for negotiation falls after 2 April 2012.

Approval No. Category
Sector Social Financial Economic Others Safeguards Project Financial Statements
Loan 1817
Loan -

Contacts and Update Details

Responsible ADB Officer ()
Responsible ADB Department Central and West Asia Department
Responsible ADB Divisions Energy Division, CWRD
Executing Agencies Barki Tajik
Mr. Samiev

Links

Project Website http://www.adb.org/projects/32513-013/main
List of Project Documents http://www.adb.org/projects/32513-013/documents